Attendees:
- T Nolan
- Linda has imphub access from EON but should create a new account with correct email
- jonathan and kempaarons each have a username I could tag for view & access permission but I can't "Usermention" him so I'm not sure what other permissions settings need to be tweaked to allow that.
Team A - ARIES infrastructure and architecture
Work Streams in Progress | Status (R/Y/G) | Actions This | Risks/Issues & Mitigation Plans | Dependencies on Other | Dogfood Targets (Milestone, System, Date) | Original Target | New Expected Release Date |
---|---|---|---|---|---|---|---|
Work stream 1 | Install the Project Status Lozenge user macro to display a visualisation of a project's status. |
| |||||
Work stream 2 | Setup between Phil Farmer (Myeloma) and Phil Taylor (SECTRA PACS) can keep projects separated by explicitly naming and selecting project-related AETitle during the send, this will help Posda keep track of parallel / concurrent submissions , Fred wants a discussion with Phil Taylor (?) | ||||||
jeff should have access to dbmi_web_1 (no ad) per LT if that's not working, Jeff should have bigger access maybe /admin or something? virtualmin has man pages. there is a way to reset from command line It will update itself to most-current, when manually triggered |
Team B - AR-CDR to ARIES stuff
Work Streams in Progress | Status (R/Y/G) | Actions This | Risks/Issues & Mitigation Plans | Dependencies on Other | Dogfood Targets (Milestone, System, Date) | Original Target | New Expected Release Date |
---|---|---|---|---|---|---|---|
Sohrab and Mahanaz and Fred are writing a paper | |||||||
Dr. Wei+Gohar's data have a table of their PatID and MRN to map to the generated ARIES ID |
Team C - ARIES with Posda stuff
Work Streams in Progress | Status (R/Y/G) | Actions This | Risks/Issues & Mitigation Plans | Dependencies on Other | Dogfood Targets (Milestone, System, Date) | Original Target | New Expected Release Date |
---|---|---|---|---|---|---|---|
Team D - ARIES Content from NDL
Work Streams in Progress | Status (R/Y/G) | Actions This | Risks/Issues & Mitigation Plans | Dependencies on Other | Dogfood Targets (Milestone, System, Date) | Original Target | New Expected Release Date |
---|---|---|---|---|---|---|---|
DICOM from scanner | Jul 31 2019 | ||||||
CIfTI from scanner | |||||||
EEG | |||||||
Neurocognitive Data | |||||||
Team E - ARIES Content from Gait lab
Work Streams in Progress | Status (R/Y/G) | Actions This | Risks/Issues & Mitigation Plans | Dependencies on Other | Dogfood Targets (Milestone, System, Date) | Original Target | New Expected Release Date |
---|---|---|---|---|---|---|---|